$4.9mm
38,000 sf
13 months
$81,000
Middletown, RI
A historical institution, St. George’s believes athletics acts as an extension of the classroom by reinforcing good sportsmanship, teamwork, self-discipline and responsibility. They desired a 40,000 SF addition to keep their ice hockey curriculum in top form amidst other competitive New England private schools.
This extensive project consisted of two phases. First, the preexisting 1960’s ice area required structural upgrades entailing replacement of the ice sheet and roof with the addition of a newly equipped machine room. The second phase entailed a pre-engineered metal building to accommodate a second new ice arena, with support facilities, ice package and stadium seating for 160. Phased to accommodate the scholastic season, the client received $81,000 back in GMP savings.